Background
The client for this project was a multilateral trade finance institution that supports the expansion, diversification, and development of trade across its member countries, including through project and export development finance.
In this engagement, the client was considering financing a new cocoa processing facility that was being developed by a subsidiary of one of the largest licensed cocoa buying companies. The plant, which was located near a major port, was designed to process over 30,000 tonnes of cocoa beans a year into cocoa liquor. The client had indicated a term loan of over USD 30 million and a larger revolving credit facility.
Problem
Cocoa is one of the world’s most valuable agricultural commodities, but producing countries typically capture only a small share of its value, as most processing takes place overseas. Producing countries are investing in local processing to keep more of that value at home, and lenders play a critical role in financing these projects, as projects of this kind frequently face significant risks. In this case, construction had been delayed after engineering, procurement, and construction (EPC) costs overran the budget, and the project’s capital requirement had risen from under USD 40 million to nearly USD 50 million, including higher EPC costs and interest during construction.
For the client, these trends presented a significant challenge and they needed independent assurance that it was technically sound, commercially viable, and bankable. It needed to know whether the key contracts with the equipment supplier and EPC contractor protected the project, whether the site, permits, and infrastructure were adequate, whether supply and offtake arrangements were secure, and whether the business case was robust. It also needed a clear view of the risks to the deal. Without this, it risked lending to a project that could face further delays or cost overruns.
Solution
Farrelly Mitchell was engaged as independent technical, commercial, and financial adviser to appraise the project. Our brief was to judge the plant’s ability to repay the facilities on offer, and the safeguards to attach to them. With that in mind, we:
- Interviewed the sponsor’s management and reviewed the data room.
- Reviewed the equipment supply and EPC contracts.
- Assessed project implementation and management options.
- Reviewed permits, site tenure, and infrastructure.
- Assessed bean supply, offtake, and market arrangements.
- Validated the revised capital costs and financial model.
- Reviewed environmental and social compliance.
- Rated risks by their impact on financial close.
Impact
The independent appraisal delivered by Farrelly Mitchell gave the client a clear, evidence-based view of the project’s strengths, risks, and the conditions needed to support financing.
The contract reviews confirmed that the core process equipment would come from a leading global supplier whose equipment is widely used across the cocoa processing industry, significantly reducing technology risk. Similarly, an evaluation of the EPC contractor, an established regional firm with more than 30 years’ experience, confirmed its ability to deliver the plant on a fixed-price turnkey basis. Farrelly Mitchell recommended proceeding with both, while addressing gaps such as the exclusion of initial spare parts from the supply contract.
An evaluation of the site confirmed that its location, tenure, zoning, and infrastructure were well suited to the plant’s needs, but found that the site coordinates in the environmental permit, and in the environmental and social impact assessment, were inconsistent. The review also assessed options for independent project management and supervision.
The financial review validated the revised capital requirement of nearly USD 50 million, reflecting updated EPC costs, interest capitalised over the two-year build, and additional working capital, and tested the model’s assumptions, which covered cocoa liquor production only. Each risk was rated according to its likely effect on financial close, distinguishing issues to resolve beforehand from those that could become conditions after close. The appraisal identified three conditions for financial close: confirming the project management contractor and agreement, signing an operations and maintenance contract for critical equipment from other suppliers, and reconciling the site coordinates.
Forge ahead with Farrelly Mitchell
All told, the engagement equipped the client to make an informed financing decision with clear conditions, offering a blueprint for lenders appraising agro-processing projects in producing countries and showing how the rigorous, data-driven advisory we deliver at Farrelly Mitchell supports high-value investment decisions. Our global presence and deep local market expertise enable us to provide insights that go beyond surface-level market overviews to deliver genuinely actionable strategic guidance.
Our comprehensive suite of advisory services includes independent technical, commercial, and financial advisory, contract reviews, financial model validation, risk assessment, and lender support. To explore how Farrelly Mitchell can support your organisation’s strategic objectives in food and agriculture, wherever you operate, contact our team today.